Barclays Corporate Office Nottingham 

Project Duration: 6 Weeks 
Project brief: install new Male WC, Female WC, Cleaners cupboard and kitchen sink 
 
 
 
 
Install new Male WC, Female WC, Cleaners cupboard and kitchen sink. 
 
ADL Mechanical and Electrical Contractors carried out this project in the evenings while the bank was closed. We removed existing sanitaryware, perimeter heating circuit, boiler and hot water heaters. 
 
We installed new mains cold water to Male WC, Female WC, Cleaners cupboard and kitchen area along with new sanitaryware, we also installed a New under sink water heater and Zip tap to the kitchen area and installed a new multi-point water heater and associated hot water pipework to WC’s and cleaners store. 